How much does a BMS upgrade cost and what are the steps?
Paweł Święch, founder and technical leader, IQ-BuildingUpdated:
A complete BMS upgrade in a modern office building of about 20,000 m² costs roughly PLN 400,000–900,000 in Poland. The cost has seven components: analysis (site survey), cabling design, cabling, detailed design, hardware, cabinet installation, and programming with commissioning. The final figure depends mostly on how much existing cabling can be reused and whether ready-made program templates can be used.
When does an upgrade stop being optional?
Controllers from established manufacturers last a long time, but they are still electronics. The real problem starts when a failed part can no longer be bought, or when the system stops receiving security fixes.
LonWorks-based systems
LonWorks was introduced by Echelon in 1990. It was formally an open standard, yet every device needed a Neuron Chip licensed by a single company. ASHRAE answered in 1995 with BACnet, a fully open standard. In 2023 the owner of the technology decided to end production of the Neuron Chip, so LON controllers can no longer be manufactured:
- Distech Controls scheduled the last deliveries of its ECL series for 30 April 2026.
- Siemens' 2025 modernisation guide marks LonWorks-based devices as end of service.
- Schneider Electric declared the TAC Xenta range fully obsolete in early 2026: no technical support, no factory service, no engineering software on its servers.
Check whether the BMS in your building communicates over LonWorks. If it does, plan the upgrade before a single failed controller forces it.
Cyber security
Older systems carry more known vulnerabilities. In May 2022 Nozomi Networks described CVE-2022-24040 in Siemens Desigo devices: repeated login attempts could take a device out of service for days. Siemens released patches, but they only help where they have been installed.
The server matters as much as the BMS software. Windows XP support ended in April 2014 and we still come across BMS servers running it. Standard support for Windows 10 ended in October 2025; Windows Server 2016 loses support in 2027.
Stages and indicative costs
Figures are for a modern office building of about 20,000 m² in Poland. Treat them as an order of magnitude for talks with a contractor, not as a quote.
| Stage | What it covers | Indicative cost |
|---|---|---|
| 1. Analysis (site survey) | Review of every building system for BMS integration, report with recommendations | PLN 10,000–20,000 |
| 2. Cabling design | Cable routes on floor plans, cable types | PLN 10,000–20,000 |
| 3. Cabling | Materials and installation | PLN 100,000–200,000 |
| 4. Detailed BMS design | Control cabinet documentation, wiring diagrams | PLN 30,000–60,000 |
| 5. Hardware | Controllers, cabinet components, server, licences | PLN 100,000–200,000 |
| 6. Cabinet build and installation | Prefabrication, swap on site, connecting field devices | PLN 50,000–100,000 |
| 7. Programming and commissioning | Controller program, user interface, testing | PLN 100,000–300,000 |
| Total | PLN 400,000–900,000 |
What happens at each stage?
On our home page we describe working with us in six stages; the table above splits the same work by what is paid for. Analysis is item 1. Engineering covers items 2, 4 and 5, cabinet prefabrication from item 6 and programming from item 7. Implementation covers item 3, on-site installation from item 6 and commissioning from item 7. Consultation and Planning are not priced as separate items here, and the stage after handover is outside this estimate.
Consultation. One of us visits the building and judges whether a full analysis makes sense.
Analysis. We review every building system, including those never connected to the BMS – often large energy consumers left out when electricity was cheap. It covers utility meters, air handling units, chillers, car park ventilation and fire systems, lighting, boilers, heat substations, switchgear, server room cooling and leak detection. The result is a report, in larger buildings several dozen pages long, that is enough to estimate a budget.
Planning. The same device can be integrated at different depths. Take trace heating on roof pipework: monitor the contactor only; let the BMS switch it by outdoor temperature; or also measure power draw. Only the last option proves the circuit is actually heating – with a tripped breaker the contactor closes, no current flows and the pipes can freeze.
Wiring check and cabling. Once the quotation is accepted we trace every connection cable by cable, design the routes around existing trays, risers and fire stopping, and keep power and signal cables apart. Cost depends on the building structure, access to trays and risers, the number of fire-stopped penetrations and how much existing cable and tray can be reused. Duration also depends on working hours: quiet work in risers and plant rooms during the day, noisy work out of hours or at weekends.
Detailed design. Wiring diagrams show every core of every cable and the terminal it lands on. They guide cabinet building and installation, and shorten fault finding for years afterwards.
Cabinets. New control cabinets arrive prefabricated and usually replace old ones on the same cables, so each swap is done in one go. Metering cabinets are swapped before the first day of the month; safety-related ones, such as car park ventilation, over a weekend; work in the main switchroom is combined with the annual transformer inspection.
Programming and commissioning. This is the largest part. Communication with air handling units, chillers, pumps, access control, the fire panel and lifts is tested during the wiring check. After installation we program the PLCs and test every sensor, device, alarm, schedule and screen.
Final checks and handover. We check the system against the specification point by point and walk the maintenance team through the new interface, because they are the ones who will get the value out of it.
Questions and answers
Does the building have to close during the upgrade?
No. Work is planned around the building: quiet tasks in the daytime, noisy ones out of hours, safety-related cabinets at weekends.
Where should we start?
With a site visit and a quick feasibility check. Only if that shows potential is the full analysis (PLN 10,000–20,000) worth commissioning.