Which remote metering mistakes cost a building owner the most?
Maciek Dembski, technical manager, IQ-BuildingUpdated:
The most expensive mistakes are the ones nobody notices: a meter that counts, but not what it should. In one office building, the cooling meters of a large tenant had the wrong register read from day one, and over about five years the building failed to bill about PLN 700,000. Day to day, most time is lost to meters that never made it into the system and to outdated documentation.
Mistake 1: the meter counts the wrong thing
In one large office building, the cooling meters in a large tenant area were misconfigured from the start. The cooling register was not active and the system read the heat register instead. With a suitable temperature difference the meter did log something, so the readings were not zero and raised no suspicion. They were, however, an order of magnitude too low. It went on for about five years and about PLN 700,000 could no longer be recovered.
A meter that “shows something” proves nothing. At commissioning every meter needs checking: type, unit, register and whether the values make sense against comparable areas.
Mistake 2: a few meters outside the system
A large building can have more than 500 meters. We often find that nearly all are read remotely and a few are not. For the maintenance team that means the same chore every month: entering tenant space, disturbing people and typing readings in by hand. We verify every meter so that all can be read remotely.
Mistake 3: outdated documentation
M-Bus is a very simple protocol: no polarity and tolerant of many errors. Even so, we see plenty of problems with it, rarely technical ones. Nobody has updated the documentation, addressing or labels, and locations on drawings do not match reality. One example: a meter above a suspended ceiling with no sticker on the tile, so the team lifts tiles one by one to find it.
What the BMS does
- Meters grouped by type and location.
- Every meter is always marked on up-to-date floor plans, which we update whenever meters are added or a fit-out changes.
- Status and date of the last successful reading for each meter.
- Daily or cumulative consumption trends and automatic Excel reports.
- A daily consumption limit per meter, with an alarm and optional e-mail when exceeded.
Limits are especially useful on water meters. In one building the limit on the irrigation meter revealed a leak: a threaded fitting had failed on a buried hose and water was running into the ground. We estimated the leak would have cost about PLN 3,500 a month.
Questions and answers
Why can a misconfigured meter go unnoticed for years?
Because it shows non-zero values. Without comparing them with other areas or expected consumption, nobody sees they are too low.